Application Window 2: October 7, 2026 – January 14, 2027. First come, first served for ready-to-build projects. Window 3 is planned for 2027 (calevip.org/fccp3).
Who it's for: property owners and businesses that want to install public DC fast chargers in California. The applicant must be both the incentive recipient and the owner of the charging equipment.
Incentives (per charging port)
- 150 kW–274.99 kW guaranteed output: $55,000
- 275 kW and up: $100,000
- Can cover up to 100% of total approved costs (equipment, installation, planning, engineering and more), up to those caps.
Key rules
- Ready to build: you need an issued permit and a final utility service design.
- Sites must be available to the public. Charging hubs, hotels and business districts are no longer eligible site types.
- At least 50% CCS connectors per site.
- Projects must follow AB 2061 data-reporting requirements.
- Disadvantaged and low-income communities are not required, but tribal, DAC and LIC applications that are ready to build get priority.
Get started
Read the Implementation Manual, use the EV Charging Opportunity Finder map, and ask for free application assistance on the CALeVIP site.
Source: CALeVIP — Fast Charge California Project Window 2, calevip.org/fccp2, and calevip.org home page (read in Chrome, checked 2026-09-28). Lead from the Nevada County News newsletter (8/13). Time-limited: update after Jan. 14, 2027.